Construction Update per email from Carl Tarpley
March 26, 2009
1. Dock Street Project Work:
Exterior – At the portico, the damaged brownstone beam has been replaced and the brownstone steps are being installed. The handicapped accessible alley to the courtyard has been poured and the brick pavers will be laid later. The courtyard storm drain lines have been installed and will be covered with brick pavers soon. Minor brick repointing continues as needed, throughout the project.
Windows – Window sash repair and reinstallation are continuing and the interior window surrounds are being built and painted.
Roofs/Attics – Miscellaneous gutter and flashing work is ongoing. Framing for the clay tile cloister roof in the courtyard has begun.
Interior – Elevator #1 installation is underway. Throughout the building utility rough-ins continue. The 3rd floor is being painted. Bathroom tile installation is in progress on the 2nd and 3rd floors. Manual paint stripping of the detailed wood work is continuing in the Wadsworth Room, the Lobby, and the Gallery. The Wadsworth Room mantels have been sent out for restoration. Stripping of the stained trim in the house, balcony, and horseshoe is ongoing.
2. Other Activity in the Vicinity of the Dock Street Theatre:
Sidewalk Repair – The Public Service Department of the City completed the sidewalk repair at 134 Church Street last week.